IMPACT Projects Abstract as on February2020 | ||||||
New Municipal Buildings | Sewage / Septage Treatment Plants | Modern Abattoirs | Gas Fired Crematoriums | Modern Markers | Total Projects | |
KIIFB Approved | 1 | 2 | 3 | 0 | 0 | 6 |
DPR Returned to LSG for Corrections | 5 | 0 | 3 | 12 | 2 | 22 |
DPR being Appraised by KIIFB | 2 | 0 | 1 | 0 | 1 | 4 |
DPR being Prepared by LSG | 2 | 11 | 4 | 13 | 8 | 38 |
Projects Rejected | 0 | 0 | 1 | 0 | 0 | 1 |
Total Projects | 10 | 13 | 12 | 25 | 11 | 71 |
For Project details kindly click on the links given below:
Establishing new Municipal Buildings
Establishing Sewage / Septage Treatment Plants
Establishing Gas Fired Crematorium
Projects Review - Cost | |||||
Sector | KIIFB Approved Projects | DPR Returned to LSG for Corrections | DPR being Appraised by KIIFB | DPR being Prepared by LSG | Total Cost in Cr. |
Building for new Municipalities | 11.14 | 60.67 | 26.79 | 6.56 | 105.16 |
Establishing Sewage / Septage Treatment Plants | 26.20 | 0 | 0 | 110 | 136.20 |
Establishing of Modern Abattoirs | 33.29 | 24.01 | 10.95 | 45 | 113.25 |
Establishing of Modern Crematoriums (Gas) | 0 | 11.44 | 0 | 12.8 | 24.24 |
Establishing of Modern Markets | 0 | 25.25 | 18 | 83 | 126.25 |
Grand Total | 70.63 | 121.37 | 55.74 | 257.36 | 505.10 |
|